Change order photo set that tells a story

Fictional rotted sill, real structure. Names are fake. Order matters more than lens price.

  1. IMG-101 — Wide: north elevation, window at left, ladder for scale. Caption: “Sill rot under dining window, found during siding pull.”
  2. IMG-102 — Medium: framing below stool, insulation pulled back. Caption: “Damage extends 28” east of jack stud; sheathing sound above.”
  3. IMG-103 — Tight: rot pocket depth, tape in frame at 2-3/4”. Caption: “Max depth at center; stud faces mostly sound.”
  4. VOX-04 — 45s voice: what you recommend (sister vs replace), what GC said on phone, when you can have material on site.

Export only these four into the CO bundle—nobody needs your lunch photo.